After the steam sterilization pot equipment is shipped to the user unit, the company will send after-sales service personnel to guide and debug. First of all, the user will set up the location of the fixed equipment, and send a special person to assist the debugging personnel to carry out the work. During the debugging process, the user dispatched the personnel to learn and install until the installation is complete, the basic layout, characteristics and working principle of the equipment have the concept. When you debug the experiment, you can get twice the result with half the effort.
Steam sterilization pot operation steps:
(1) Loading: Push the goods into the pot, close the pot door and self-locking device, and then inject 0.1Mpa into the country and close it.
(2) Temperature rise: open the steam valve to raise the temperature. When the pressure in the pot is 0.2Mpa, open the exhaust valve to exhaust, pay attention to the pressure balance. When the temperature shows the temperature to the sterilization requirement, close the steam and drain valve.
(3) Sterilization: If the temperature and pressure drop during the heat preservation period, the steam is heated or pressurized. On the contrary, the cold pressure and steam are required to be replenished, and the temperature and pressure are equalized to the sterilization time.
(4) Cooling: Open the drain steam valve, turn off the water pump to the drain steam valve when the water is sprayed, and open the water inlet valve to cool the water. Pay attention to the pressure inside the pot at this time, such as lowering the fill valve. On the contrary, the exhaust valve is exhausted. When the overflow valve overflows, open the overflow valve and drain the upper layer of hot water in the pot. When the temperature of the thermometer is 40, open the spray valve to close, the flooding valve and the overflow valve open, and the drain valve continues to cool in the water (note Keep the pressure balanced. When the thermometer shows a temperature below 30, turn off the spray, drain the valve, and stop the pump. Allow the goods to soak in cold water for 5-10 minutes, drain, open, and ship, and sterilize